NRG THW GT 345 (TEF -Due Diligence) — Project Summary

Queue ID
ERCOT-24INR0482
Capacity
456 MW
Technology
Gas
Status
active
Location
Harris, TX
Region
ERCOT
Developer
NRG THW GT LLC
IA Status
IA Executed

NRG THW GT 345 (TEF -Due Diligence)

ERCOT-24INR0482BetaActiveGasERCOTLBNL + Live

456 MW generation in Harris, TX · In queue since November 2022 · Proposed COD May 2026

456 MW

Capacity

1

Components

Gas

3y 5m

In Queue

IA Executed

IA Status

Signed Aug 2024

Interconnection Timeline

Queue → IA

1y 9m

IA → COD

1y 9m

Total Duration

1y 9m

Construction75%
Queue EntryNov 17, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 22, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2026-05-01

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

NRG THW GT LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

345 kV Bus Number: 45500, Bus Name: T_H_W__POI_5

Data Source

LBNL + Live

Linked EIA Plant

NRG THW GT Electric Generating Station

EIA Plant ID: 66601

View Plant
No news available for this project.