Barrett Solar
125.81 MW generation in Rains, TX · In queue since February 2023 · Proposed COD March 2026
125.81 MW
Capacity
1
Components
Solar
3y 2m
In Queue
IA Executed
IA Status
Signed Oct 2023
Queue → IA
8 months
IA → COD
2y 5m
Total Duration
8 months
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-16
State
TX
County
Rains
Region
ERCOT
Developer
Barrett Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 6798 SNYPT_RC - 6797 LNOK_RC 138kV line