Hooper Solar
BetaActiveSolarERCOTLBNL + Live
50.48 MW generation in Lee, TX · In queue since December 2022 · Proposed COD December 2027
50.48 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntryDec 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-15
Project Details
State
TX
County
Lee
Region
ERCOT
Developer
BT Brown Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV line between Lexington (Bus #7571) and Lyle Wolz (Bus #7567)
Data Source
LBNL + Live
No news available for this project.