Evelyn Battery Energy Storage System — Project Summary

Queue ID
ERCOT-24INR0460
Capacity
221.3 MW
Technology
Battery
Status
active
Location
Galveston, TX
Region
ERCOT
Developer
Evelyn Energy Storage LLC
IA Status
IA Executed

Evelyn Battery Energy Storage System

BetaActiveBatteryERCOTLBNL

221.3 MW storage in Galveston, TX · In queue since January 2023 · Proposed COD June 2025

221.3 MW

Capacity

1

Components

Battery

3y 2m

In Queue

IA Executed

IA Status

Signed Sep 2023

Interconnection Timeline

Queue → IA

8 months

IA → COD

1y 9m

Total Duration

8 months

Schedule

9 months past proposed COD

Construction75%
Queue EntryJan 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 14, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-06-30

Project Details

State

TX

County

Galveston

Region

ERCOT

Developer

Evelyn Energy Storage LLC

Utility

Entity

ERCOT

Point of Interconnection

Hidden Lakes 138kV (38900)

Data Source

LBNL

No news available for this project.