FRIENDSWOOD ENERGY GENCO
143.7 MW generation in Harris, TX · In queue since December 2022 · Proposed COD March 2026
143.7 MW
Capacity
1
Components
Gas
3y 4m
In Queue
IA Executed
IA Status
Signed Apr 2024
Queue → IA
1y 4m
IA → COD
1y 11m
Total Duration
1y 4m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2026-03-21
State
TX
County
Harris
Region
ERCOT
Developer
Tejas Power Generation LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
47170 H O CLARKE 138KV
Data Source
LBNL + Live
Linked EIA Plant
Friendswood Energy
EIA Plant ID: 60468