Starling Solar Phase II — Project Summary

Queue ID
ERCOT-24INR0440
Capacity
43.56 MW
Technology
Solar
Status
active
Location
Gonzales, TX
Region
ERCOT
Developer
Starling Solar, LLC
IA Status
Facility Study

Starling Solar Phase II

BetaActiveSolarERCOTLBNL + Live

43.56 MW generation in Gonzales, TX · In queue since October 2022 · Proposed COD January 2028

43.56 MW

Capacity

1

Components

Solar

3y 5m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 3m

Facilities Study50%
Queue EntryOct 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-28

Project Details

State

TX

County

Gonzales

Region

ERCOT

Developer

Starling Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 7224 Luling - 7245 Gonzales. Starling Solar Phase II is a an addition of 42.24MW to the 23INR0035 (solar) filed in 2020. 23INR0181 (storage) was filed in 2021.

Data Source

LBNL + Live