Umbra Solar II
BetaSuspendedSolarERCOTLBNL
344.66 MW generation in Franklin, TX · In queue since June 2023
344.66 MW
Capacity
1
Components
Solar
2y 9m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
2y 9m
Suspended0%
Queue EntryJun 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Franklin
Region
ERCOT
Developer
—
Utility
—
Entity
ERCOT
Data Source
LBNL
No news available for this project.