Two Brothers Battery Energy Storage System — Project Summary

Queue ID
ERCOT-24INR0425
Capacity
152 MW
Technology
Battery
Status
active
Location
Victoria, TX
Region
ERCOT
Developer
BRP Blue Topaz 2, LLC
IA Status
IA Executed

Two Brothers Battery Energy Storage System

ERCOT-24INR0425BetaActiveBatteryERCOTLBNL + Live

152 MW storage in Victoria, TX · In queue since September 2022 · Proposed COD September 2027

152 MW

Capacity

1

Components

Battery

3y 7m

In Queue

IA Executed

IA Status

Signed Apr 2024

Interconnection Timeline

Queue → IA

1y 7m

IA → COD

3y 5m

Total Duration

1y 7m

Construction75%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 22, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-09-09

Project Details

State

TX

County

Victoria

Region

ERCOT

Developer

BRP Blue Topaz 2, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

8911 BLKBYU4A 138kV

Data Source

LBNL + Live

No news available for this project.