Two Brothers Battery Energy Storage System
ERCOT-24INR0425BetaActiveBatteryERCOTLBNL + Live
152 MW storage in Victoria, TX · In queue since September 2022 · Proposed COD September 2027
152 MW
Capacity
1
Components
Battery
3y 7m
In Queue
IA Executed
IA Status
Signed Apr 2024
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
3y 5m
Total Duration
1y 7m
Construction75%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 22, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-09-09
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
BRP Blue Topaz 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8911 BLKBYU4A 138kV
Data Source
LBNL + Live
No news available for this project.