Hollow Branch Creek Solar — Project Summary

Queue ID
ERCOT-24INR0422
Capacity
460 MW
Technology
Solar
Status
active
Location
Leon, TX
Region
ERCOT
Developer
IA Status

Hollow Branch Creek Solar

ERCOT-24INR0422BetaActiveSolarERCOTLBNL + Live

460 MW generation in Leon, TX · In queue since September 2022 · Proposed COD June 2028

460 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Status

Signed Oct 2024

Interconnection Timeline

Queue → IA

2y 1m

IA → COD

3y 8m

Total Duration

2y 1m

Construction0%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 22, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-06-30

Project Details

State

TX

County

Leon

Region

ERCOT

Developer

Utility

Entity

ERCOT

Service Type

Data Source

LBNL + Live