Hollow Branch Creek Solar
ERCOT-24INR0422BetaActiveSolarERCOTLBNL + Live
460 MW generation in Leon, TX · In queue since September 2022 · Proposed COD June 2028
460 MW
Capacity
1
Components
Solar
3y 7m
In Queue
—
IA Status
Signed Oct 2024
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
3y 8m
Total Duration
2y 1m
Construction0%
Queue EntrySep 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 22, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Leon
Region
ERCOT
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
No news available for this project.