Furay Battery Energy Storage System — Project Summary

Queue ID
ERCOT-24INR0413
Capacity
304 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Blue Topaz 1, LLC
IA Status
Facility Study

Furay Battery Energy Storage System

BetaActiveBatteryERCOTLBNL + Live

304 MW storage in Harris, TX · In queue since September 2022 · Proposed COD September 2028

304 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6 years

Facilities Study50%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Blue Topaz 1, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 45660 Jonte substation _x0013_ 46332 Scenic Woods Tapping both radial lines.

Data Source

LBNL + Live

No news available for this project.