Camino Ranch Solar SLF
ERCOT-24INR0412BetaActiveSolarERCOTLBNL + Live
296.42 MW generation in Houston, TX · In queue since October 2022 · Proposed COD December 2028
296.42 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 2m
Facilities Study50%
Queue EntryOct 6, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-09
Project Details
State
TX
County
Houston
Region
ERCOT
Developer
Camino Ranch Solar Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap to Jim English (#3351) _x0013_ Flat Branch (#3345) 138kV
Data Source
LBNL + Live
No news available for this project.