Greens Bayou Unit 9 CT 345
BetaActiveGasERCOTLBNL
455 MW generation in Harris, TX · In queue since September 2022 · Proposed COD June 2026
455 MW
Capacity
1
Components
Gas
3y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 9m
Facilities Study50%
Queue EntrySep 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-02
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
NRG Texas Power LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Position 1/0 PSSE 40700, Greens Bayou Substation
Data Source
LBNL