Mercury Solar III
BetaActiveSolarERCOTLBNL + Live
203.5 MW generation in Hill, TX · In queue since August 2022 · Proposed COD April 2029
203.5 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 8m
Facilities Study50%
Queue EntryAug 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-01
Project Details
State
TX
County
Hill
Region
ERCOT
Developer
Mercury Solar
Utility
—
Entity
ERCOT
Point of Interconnection
68092 Liberty Station 345kV
Data Source
LBNL + Live
No news available for this project.