Buzios Solar
252 MW generation in Motley, TX · In queue since September 2022 · Proposed COD January 2026
252 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 2m
IA → COD
2y 2m
Total Duration
1y 2m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-01-30
State
TX
County
Motley
Region
ERCOT
Developer
Roaring Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap between Cottonwood (#59904) and White River (#23922)