Buzios Solar — Project Summary

Queue ID
ERCOT-24INR0399
Capacity
252 MW
Technology
Solar
Status
active
Location
Motley, TX
Region
ERCOT
Developer
Roaring Springs Solar, LLC
IA Status
IA Executed

Buzios Solar

ERCOT-24INR0399BetaActiveSolarERCOTLBNL + Live

252 MW generation in Motley, TX · In queue since September 2022 · Proposed COD January 2026

252 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Executed

IA Status

Signed Nov 2023

Interconnection Timeline

Queue → IA

1y 2m

IA → COD

2y 2m

Total Duration

1y 2m

Schedule

2 months past proposed COD

Construction75%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 6, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-01-30

Project Details

State

TX

County

Motley

Region

ERCOT

Developer

Roaring Springs Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap between Cottonwood (#59904) and White River (#23922)

Data Source

LBNL + Live