Destiny Storage — Project Summary

Queue ID
ERCOT-24INR0397
Capacity
205.57 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Destiny Storage, LLC
IA Status
IA Executed

Destiny Storage

ERCOT-24INR0397BetaActiveBatteryERCOTLBNL + Live

205.57 MW storage in Harris, TX · In queue since August 2022 · Proposed COD May 2026

205.57 MW

Capacity

1

Components

Battery

3y 8m

In Queue

IA Executed

IA Status

Signed Sep 2023

Interconnection Timeline

Queue → IA

1y 1m

IA → COD

2y 8m

Total Duration

1y 1m

Construction75%
Queue EntryAug 16, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 20, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-05-20

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Destiny Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 40390 Crosby - 40680 Placid Ckt 86

Data Source

LBNL + Live

Linked EIA Plant

Destiny Storage

EIA Plant ID: 67654

View Plant
No news available for this project.