Riverwalk BESS
BetaActiveBatteryERCOTLBNL + Live
120 MW storage in Bexar, TX · In queue since July 2022 · Proposed COD October 2027
120 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 3m
Facilities Study50%
Queue EntryJul 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
RWE Solar Developement, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5294 Martinez Substation 138kV
Data Source
LBNL + Live
No news available for this project.