Remy Jade III Power Station — Project Summary

Queue ID
ERCOT-24INR0382
Capacity
102 MW
Technology
Gas
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Remy Jade III Generating, LLC
IA Status
IA Executed

Remy Jade III Power Station

ERCOT-24INR0382BetaActiveGasERCOTLBNL + Live

102 MW generation in Harris, TX · In queue since July 2022 · Proposed COD May 2028

102 MW

Capacity

1

Components

Gas

3y 9m

In Queue

IA Executed

IA Status

Signed Aug 2022

Interconnection Timeline

Queue → IA

1 month

IA → COD

5y 9m

Total Duration

1 month

Construction75%
Queue EntryJul 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 1, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Remy Jade III Generating, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 40390 Crosby - 40811 Highlands

Data Source

LBNL + Live

No news available for this project.