Possum Kingdom BESS
BetaActiveBatteryERCOTLBNL + Live
200.86 MW storage in Jack, TX · In queue since September 2022 · Proposed COD October 2027
200.86 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
Facilities Study50%
Queue EntrySep 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-29
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
PK Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 1421 Willow Creek _x0013_ 11523 Thomas Price
Data Source
LBNL + Live
No news available for this project.