Farrier Station Energy Storage — Project Summary

Queue ID
ERCOT-24INR0374
Capacity
409.9 MW
Technology
Battery
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
Farrier Station Energy Storage Project, LLC
IA Status
Facility Study

Farrier Station Energy Storage

BetaActiveBatteryERCOTLBNL

409.9 MW storage in Hopkins, TX · In queue since January 2023 · Proposed COD June 2028

409.9 MW

Capacity

1

Components

Battery

3y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryJan 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

TX

County

Hopkins

Region

ERCOT

Developer

Farrier Station Energy Storage Project, LLC

Utility

Entity

ERCOT

Point of Interconnection

MONTICELLO SES (BUS# 1696) - ALLEN SWITCH (BUS# 2514)

Data Source

LBNL