Pitts Dudik II
ERCOT-24INR0364BetaActiveSolarERCOTLBNL + Live
30.23 MW generation in Hill, TX · In queue since July 2022 · Proposed COD April 2026
30.23 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Jun 2024
Interconnection Timeline
Queue → IA
1y 11m
IA → COD
1y 10m
Total Duration
1y 11m
Construction75%
Queue EntryJul 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 13, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-04-24
Project Details
State
TX
County
Hill
Region
ERCOT
Developer
Pitts Dudik II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Ash Creek Switch (#3473)
Data Source
LBNL + Live
No news available for this project.