Cibeles Solar
ERCOT-24INR0356BetaActiveSolarERCOTLBNL + Live
251 MW generation in Mclennan, TX · In queue since May 2022 · Proposed COD June 2027
251 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
Facilities Study50%
Queue EntryMay 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Mclennan
Region
ERCOT
Developer
Elawan Cibeles Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 68090 Sam Switch _x0013_ 13405 Tradinghouse SES
Data Source
LBNL + Live