Anatole Renewable Energy Storage
207.82 MW storage in Henderson, TX · In queue since June 2022 · Proposed COD March 2027
207.82 MW
Capacity
1
Components
Battery
3y 10m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
1y 11m
IA → COD
2y 10m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-03-31
State
TX
County
Henderson
Region
ERCOT
Developer
Eustace Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(Bus# 6951) Eustace Southeast 138kV Substation (owned by Rayburn Electric Cooperative)