Exodus Solar
BetaActiveSolarERCOTLBNL
181.02 MW generation in Caldwell, TX · In queue since June 2022 · Proposed COD May 2026
181.02 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryJun 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-01
Project Details
State
TX
County
Caldwell
Region
ERCOT
Developer
Exodus Solar LLC.
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 7040 Austrop _x0013_ 7042 Zorn
Data Source
LBNL
No news available for this project.