Guinness BESS — Project Summary

Queue ID
ERCOT-24INR0352
Capacity
100.51 MW
Technology
Battery
Status
active
Location
Williamson, TX
Region
ERCOT
Developer
Momentum Energy Storage Partners,LLC
IA Status
Facility Study

Guinness BESS

BetaActiveBatteryERCOTLBNL + Live

100.51 MW storage in Williamson, TX · In queue since July 2022 · Proposed COD April 2027

100.51 MW

Capacity

1

Components

Battery

3y 8m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 9m

Facilities Study50%
Queue EntryJul 25, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-15

Project Details

State

TX

County

Williamson

Region

ERCOT

Developer

Momentum Energy Storage Partners,LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 7520 BERTRA - 7522 ANDICE

Data Source

LBNL + Live

No news available for this project.