Mystic Springs Renewable Energy Solar SLF
ERCOT-24INR0339BetaActiveSolarERCOTLBNL + Live
258.83 MW generation in Kaufman, TX · In queue since May 2022 · Proposed COD March 2028
258.83 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 10m
Facilities Study50%
Queue EntryMay 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-31
Project Details
State
TX
County
Kaufman
Region
ERCOT
Developer
Tawakoni Park Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Royse Switch (2478) _x0013_ Poetry Switch (2485)
Data Source
LBNL + Live