Eldora Solar
ERCOT-24INR0337BetaActiveSolarERCOTLBNL + Live
200.94 MW generation in Matagorda, TX · In queue since June 2022 · Proposed COD July 2028
200.94 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
1y 5m
IA → COD
4y 8m
Total Duration
1y 5m
Construction75%
Queue EntryJun 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 15, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-07-02
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
Eldora Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 5915 South Texas Project _x0013_ 44200 Hillje Ckt 1
Data Source
LBNL + Live
No news available for this project.