Chisme Solar
BetaActiveSolarERCOTLBNL + Live
147 MW generation in Brown, TX · In queue since January 2023 · Proposed COD April 2027
147 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntryJan 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-13
Project Details
State
TX
County
Brown
Region
ERCOT
Developer
Blue Heron Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 1444 BROWN SWITCH - 3424 BUCKHORN SWITCH
Data Source
LBNL + Live
No news available for this project.