TRAVIS KIMBRO BESS
BetaActiveBatteryERCOTLBNL
36.84 MW storage in Travis, TX · In queue since September 2022 · Proposed COD September 2028
36.84 MW
Capacity
1
Components
Battery
3y 6m
In Queue
IA Executed
IA Status
Signed Oct 2024
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
3y 11m
Total Duration
2y 1m
Construction75%
Queue EntrySep 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 31, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-09-18
Project Details
State
TX
County
Travis
Region
ERCOT
Developer
Travis Kimbro BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
7337 Kimbro 138kV
Data Source
LBNL
No news available for this project.