Burro Loco Energy Storage — Project Summary

Queue ID
ERCOT-24INR0319
Capacity
25.14 MW
Technology
Battery
Status
active
Location
Cameron, TX
Region
ERCOT
Developer
VESI
IA Status
Facility Study

Burro Loco Energy Storage

BetaActiveBatteryERCOTLBNL + Live

25.14 MW storage in Cameron, TX · In queue since July 2022 · Proposed COD September 2028

25.14 MW

Capacity

1

Components

Battery

3y 8m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 2m

Facilities Study50%
Queue EntryJul 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-15

Project Details

State

TX

County

Cameron

Region

ERCOT

Developer

VESI

Utility

Entity

ERCOT

Point of Interconnection

8626 Resaca 69kV

Data Source

LBNL + Live

No news available for this project.