Black Springs BESS
BetaActiveBatteryERCOTLBNL
120.68 MW storage in Palo Pinto, TX · In queue since April 2022 · Proposed COD October 2025
120.68 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
Signed Oct 2023
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
2 years
Total Duration
1y 6m
Schedule
5 months past proposed COD
Construction75%
Queue EntryApr 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 18, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-10-15
Project Details
State
TX
County
Palo Pinto
Region
ERCOT
Developer
Black Springs BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1571 ORAN 138KV
Data Source
LBNL