MRG Goody Storage
50.4 MW storage in Lamar, TX · In queue since May 2022 · Proposed COD March 2026
50.4 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 6m
IA → COD
2y 4m
Total Duration
1y 6m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-03-20