Erika Solar
ERCOT-24INR0303BetaActiveSolarERCOTLBNL + Live
204.08 MW generation in Kaufman, TX · In queue since July 2022 · Proposed COD June 2027
204.08 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Oct 2023
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
3y 8m
Total Duration
1y 3m
Construction75%
Queue EntryJul 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 12, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Kaufman
Region
ERCOT
Developer
Erika Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)
Data Source
LBNL + Live