Leighton Solar SLF — Project Summary

Queue ID
ERCOT-24INR0298
Capacity
183 MW
Technology
Solar
Status
active
Location
Limestone, TX
Region
ERCOT
Developer
Lavender Solar LLC
IA Status
IA Executed

Leighton Solar SLF

ERCOT-24INR0298BetaActiveSolarERCOTLBNL + Live

183 MW generation in Limestone, TX · In queue since May 2022 · Proposed COD September 2027

183 MW

Capacity

1

Components

Solar

3y 11m

In Queue

IA Executed

IA Status

Signed May 2024

Interconnection Timeline

Queue → IA

2 years

IA → COD

3y 4m

Total Duration

2 years

Construction75%
Queue EntryMay 11, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 28, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

TX

County

Limestone

Region

ERCOT

Developer

Lavender Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

99 BENHUR 69kV

Data Source

LBNL + Live

No news available for this project.