Leighton Solar SLF
ERCOT-24INR0298BetaActiveSolarERCOTLBNL + Live
183 MW generation in Limestone, TX · In queue since May 2022 · Proposed COD September 2027
183 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
Signed May 2024
Interconnection Timeline
Queue → IA
2 years
IA → COD
3y 4m
Total Duration
2 years
Construction75%
Queue EntryMay 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 28, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-09-01
Project Details
State
TX
County
Limestone
Region
ERCOT
Developer
Lavender Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
99 BENHUR 69kV
Data Source
LBNL + Live
No news available for this project.