Citrus Flatts BESS
ERCOT-24INR0294BetaActiveBatteryERCOTLBNL + Live
100.8 MW storage in Cameron, TX · In queue since March 2022 · Proposed COD May 2026
100.8 MW
Capacity
1
Components
Battery
4y 1m
In Queue
IA Executed
IA Status
Signed Sep 2023
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
2y 8m
Total Duration
1y 6m
Construction75%
Queue EntryMar 30, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 8, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-05-16
Project Details
State
TX
County
Cameron
Region
ERCOT
Developer
Citrus Flatts Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80022 Oleander 138kV
Data Source
LBNL + Live
No news available for this project.