Rockridge Solar Project — Project Summary

Queue ID
ERCOT-24INR0287
Capacity
221.27 MW
Technology
Solar
Status
active
Location
Guadalupe, TX
Region
ERCOT
Developer
Magnolia Solar Development LLC
IA Status
Facility Study

Rockridge Solar Project

ERCOT-24INR0287BetaActiveSolarERCOTLBNL + Live

221.27 MW generation in Guadalupe, TX · In queue since April 2022 · Proposed COD April 2027

221.27 MW

Capacity

1

Components

Solar

4 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5 years

Facilities Study50%
Queue EntryApr 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-03

Project Details

State

TX

County

Guadalupe

Region

ERCOT

Developer

Magnolia Solar Development LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

7225 Hickory Forest 138kV

Data Source

LBNL + Live

No news available for this project.