APV Plumwood Storage
ERCOT-24INR0285BetaActiveBatteryERCOTLBNL + Live
200.82 MW storage in Chambers, TX · In queue since March 2022 · Proposed COD May 2027
200.82 MW
Capacity
1
Components
Battery
4y 1m
In Queue
IA Executed
IA Status
Signed Sep 2024
Interconnection Timeline
Queue → IA
2y 6m
IA → COD
2y 8m
Total Duration
2y 6m
Construction75%
Queue EntryMar 30, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 3, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-05-01
Project Details
State
TX
County
Chambers
Region
ERCOT
Developer
APV Lonestar Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 40171 Baytown - 40015Cedar Bayou Plant
Data Source
LBNL + Live
No news available for this project.