Port Bay ESC — Project Summary

Queue ID
ERCOT-24INR0280
Capacity
200 MW
Technology
Battery
Status
active
Location
Aransas, TX
Region
ERCOT
Developer
FRESH AIR ENERGY II, LLC
IA Status
Facility Study

Port Bay ESC

BetaActiveBatteryERCOTLBNL

200 MW storage in Aransas, TX · In queue since March 2022 · Proposed COD June 2027

200 MW

Capacity

1

Components

Battery

4 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 3m

Facilities Study50%
Queue EntryMar 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-28

Project Details

State

TX

County

Aransas

Region

ERCOT

Developer

FRESH AIR ENERGY II, LLC

Utility

Entity

ERCOT

Point of Interconnection

8434 Rockport Substation (ROCKPORT4A) 138kV

Data Source

LBNL

No news available for this project.