Picadillo BESS
ERCOT-24INR0275BetaActiveBatteryERCOTLBNL + Live
100.83 MW storage in Martin, TX · In queue since March 2022 · Proposed COD May 2028
100.83 MW
Capacity
1
Components
Battery
4y 1m
In Queue
IA Executed
IA Status
Signed Jan 2024
Interconnection Timeline
Queue → IA
1y 10m
IA → COD
4y 4m
Total Duration
1y 10m
Construction75%
Queue EntryMar 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJan 23, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-05-15
Project Details
State
TX
County
Martin
Region
ERCOT
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23837 Buffalo 138kV
Data Source
LBNL + Live