Cold Creek Solar
BetaActiveSolarERCOTLBNL
455 MW generation in Schleicher, TX · In queue since April 2022 · Proposed COD December 2026
455 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 8m
Facilities Study50%
Queue EntryApr 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Schleicher
Region
ERCOT
Developer
Cold Creek Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
76003 Big Hill Substation 345kV
Data Source
LBNL
No news available for this project.