Lager Storage
BetaActiveBatteryERCOTLBNL + Live
31.1 MW storage in Nueces, TX · In queue since February 2022 · Proposed COD June 2028
31.1 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 4m
Facilities Study50%
Queue EntryFeb 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Nueces
Region
ERCOT
Developer
Momentum Lager LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8031 Gillrina 69kV
Data Source
LBNL + Live
No news available for this project.