Zeissel Solar
ERCOT-24INR0258BetaActiveSolarERCOTLBNL + Live
457.5 MW generation in Knox, TX · In queue since February 2022 · Proposed COD June 2028
457.5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Status
Signed Feb 2024
Interconnection Timeline
Queue → IA
2 years
IA → COD
4y 4m
Total Duration
2 years
Construction75%
Queue EntryFeb 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 24, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Knox
Region
ERCOT
Developer
ZSS Power, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60700 Gauss 345 KV
Data Source
LBNL + Live
No news available for this project.