Kennedy Solar
101.5 MW generation in Navarro, TX · In queue since March 2022 · Proposed COD December 2028
101.5 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
State
TX
County
Navarro
Region
ERCOT
Developer
Kennedy Bypass Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
Data Source
LBNL + Live
US court approves Amazon acquisition of 1.2 GW Oregon solar project
A US bankruptcy court approved Amazon's purchase of the 1.2 GW Sunstone solar and battery storage project in Oregon from bankrupt developer...
US court approves Amazon acquisition of 1.2 GW Oregon solar project
A US bankruptcy court approved Amazon's purchase of the 1.2 GW Sunstone solar and battery storage project in Oregon from bankrupt developer...
US court approves Amazon acquisition of 1.2 GW Oregon solar project
A US bankruptcy court approved Amazon's purchase of the 1.2 GW Sunstone solar and battery storage project in Oregon from bankrupt developer...
Sun Shines on FPL’s Solar Program
Florida provides a wealth of opportunity for utilities building a solar power portfolio, and Florida Power & Light has taken a lead role...
Last updated 2026-03-26