Kruth Storage — Project Summary

Queue ID
ERCOT-24INR0252
Capacity
203 MW
Technology
Battery
Status
active
Location
Angelina, TX
Region
ERCOT
Developer
Martinez Energy Storage LLC
IA Status
Facility Study

Kruth Storage

BetaActiveBatteryERCOTLBNL

203 MW storage in Angelina, TX · In queue since February 2022 · Proposed COD March 2026

203 MW

Capacity

1

Components

Battery

4y 1m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 1m

Facilities Study50%
Queue EntryFeb 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

TX

County

Angelina

Region

ERCOT

Developer

Martinez Energy Storage LLC

Utility

Entity

ERCOT

Point of Interconnection

3319 Redland 138kV

Data Source

LBNL

No news available for this project.