Kruth Storage
BetaActiveBatteryERCOTLBNL
203 MW storage in Angelina, TX · In queue since February 2022 · Proposed COD March 2026
203 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 1m
Facilities Study50%
Queue EntryFeb 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
TX
County
Angelina
Region
ERCOT
Developer
Martinez Energy Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
3319 Redland 138kV
Data Source
LBNL
No news available for this project.