Sultan BESS
BetaActiveBatteryERCOTLBNL
203.8 MW storage in Bosque, TX · In queue since March 2022 · Proposed COD July 2027
203.8 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 4m
Facilities Study50%
Queue EntryMar 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-08
Project Details
State
TX
County
Bosque
Region
ERCOT
Developer
Sultan BESS
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 68080 Sam Switch _x0013_ 68090 Kopperl
Data Source
LBNL