Diamondback BESS
BetaActiveBatteryERCOTLBNL
203.8 MW storage in Starr, TX · In queue since March 2022 · Proposed COD June 2030
203.8 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
8y 3m
Facilities Study50%
Queue EntryMar 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-30
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
Diamondback BESS
Utility
—
Entity
ERCOT
Point of Interconnection
80355 Del Sol 345kV
Data Source
LBNL
No news available for this project.