Whitethorn Solar — Project Summary

Queue ID
ERCOT-24INR0240
Capacity
274.83 MW
Technology
Solar
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
Greasewood III LLC
IA Status
Facility Study

Whitethorn Solar

BetaActiveSolarERCOTLBNL

274.83 MW generation in Pecos, TX · In queue since May 2022 · Proposed COD May 2027

274.83 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5 years

Facilities Study50%
Queue EntryMay 11, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-01

Project Details

State

TX

County

Pecos

Region

ERCOT

Developer

Greasewood III LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 76002 Bakerfield - 60404 Solstice CKT#1

Data Source

LBNL

No news available for this project.