Rock N' Roll Storage Two — Project Summary

Queue ID
ERCOT-24INR0235
Capacity
206 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Rock N' Roll Solar, LLC
IA Status
Facility Study

Rock N' Roll Storage Two

BetaActiveBatteryERCOTLBNL + Live

206 MW storage in Brazoria, TX · In queue since February 2022 · Proposed COD August 2027

206 MW

Capacity

1

Components

Battery

4y 1m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 6m

Facilities Study50%
Queue EntryFeb 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-30

Project Details

State

TX

County

Brazoria

Region

ERCOT

Developer

Rock N' Roll Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 44600 Rosharon - 44531 Winmil

Data Source

LBNL + Live