Owens Solar
BetaActiveSolarERCOTLBNL
203.5 MW generation in Bosque, TX · In queue since February 2022 · Proposed COD December 2025
203.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 10m
Schedule
3 months past proposed COD
Facilities Study50%
Queue EntryFeb 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
TX
County
Bosque
Region
ERCOT
Developer
Owens Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV line between 177 BOSQUE and 181 Cayote
Data Source
LBNL