Eastbell Milam Solar II
150.6 MW generation in Milam, TX · In queue since March 2022 · Proposed COD November 2025
150.6 MW
Capacity
1
Components
Solar
4y 1m
In Queue
IA Executed
IA Status
Signed Oct 2023
Queue → IA
1y 7m
IA → COD
2y 1m
Total Duration
1y 7m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-11-27
State
TX
County
Milam
Region
ERCOT
Developer
Cattlemen Solar Park II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2