Glasgow Storage
ERCOT-24INR0207BetaActiveBatteryERCOTLBNL + Live
101 MW storage in Navarro, TX · In queue since February 2022 · Proposed COD March 2028
101 MW
Capacity
1
Components
Battery
4y 2m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
1y 9m
IA → COD
4y 4m
Total Duration
1y 9m
Construction75%
Queue EntryFeb 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 8, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-03-16
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Glasgow Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV line between BUS #2466 Big Onion to #68091 Navarro circuit
Data Source
LBNL + Live